Home Boona FM News Mbarara contractor warned over delayed road works

Mbarara contractor warned over delayed road works

19

MICHAEL

Officials from the public procurement and disposal of public assets Authority (PPDA) have threatened to terminate the contract awarded to MULTIPLEX company for the delayed construction works on three roads in Mbarara city.

In May last year, 2021 Mbarara city council awarded a contract to MULTIPLEX to work on three city roads which include Stanley Road 0.78Km, Major victor Bwana Road 0.95km, Galt Road 0.63Km at a cost of 23 billion, which were projected to last only 12 months but surprisingly the contractor has not even delivered half of 50 percent.

While monitoring the ongoing works on Friday in Mbarara city, Benson Turamye the Executive Director of PPDA says the contract was scheduled to be completed by 18. 05.2022 but the work is behind schedule  

He adds that the government consultant will audit the remaining portion of work before awarding the contractor more time.

 However, Moses Bbosa the managing director of MULTIPLEX is convinced that works on the three city roads will be done if they are given a five-month contract extension.

He adds that they have encountered a number of challenges ranging from electricity poles and water pipes laid by the National Water and sewerage corporation and blamed Mbarara city council authorities who never cleared the site in time.

The city mayor Mbarara city Robert Mugabe Kakyebezi called on MULTIPLEX officials to utilize the extension period which will be granted to them profitably in order to deliver the stalled project within that specific time frame.